Planned Maintenance: London Telehouse

By | 6:17 pm 08 December 2009

Thursday 17th December 2009, 00:00  to 04:00 During the above time slot we will be replacing our core switches in Telehouse East London and connecting the final leg of the new Coventry ring. We will be deploying the new switches in parallel with the existing and we will then migrate customer, backhaul  and upstream connections… Read More »

Planned Maintenance: Coventry Hosting

By | 6:07 pm 08 December 2009

Wednesday 9th December 2009, 21:00  to 00:00 During the above time slot we will be replacing our core switches at our Coventry Data Centre. We will be deploying the new switches in parallel with the existing and we will then migrate customers connections one at a time. We are therefore only anticipating customer connections to… Read More »